Application forms and information sheets:
- Works in a Thoroughfare permit and Traffic Management Plan assessment application form
- Traffic count application
Traffic management plans require a minimum assessment time once an application is submitted of:
- 10 working days to the start date of works
If works require Temporary Thoroughfare Closure, assessment time for application is:
- a minimum of 3 weeks for closures less than 4 weeks
- a minimum of 6 weeks for closures more than 4 weeks
In addition, please note below:
• Traffic Management Plan designer / Reviewer Accreditations must be either ATWM / RTM